The additions are currently being designed, and are slated to include a new multi-purpose room, expanded support services spaces and approximately 4 new classrooms and associated corridor space. The finishes in the addition will compliment and be consistent with those found in the existing facility after renovations have been completed. HVAC renovations are also slated for the auditorium and music area portions of the existing building. The school district is hopeful that the Avon Lake community will agree with the need for this project and vote to support the bond issue on November 3, 2009.
|
Summary:
Learwood Middle School will undergo focused renovations
to its 109,821 SF of existing building area in conjunction with modest additions of approximately 13,017 square feet.
New Project Data:
Students: 709
Grades: 7-8
Building area: 122,838